BITEC — Exhibitor and Contractor Reference Guide
Venue Reference

BITEC — Exhibitor and Contractor Reference Guide

Operational reference for BITEC Bang Na exhibitors — build-up windows, contractor registration, stand height rules, rigging and power ordering.

Rules, specifications and build-up schedules change between event editions and must be confirmed against the current exhibitor manual for your specific show. Last reviewed: 18 August 2026.

Bangkok International Trade & Exhibition Centre (BITEC) is a purpose-built exhibition campus on Bang Na-Trat Road at km 1, approximately 20 km from central Bangkok and 15 km from Suvarnabhumi Airport. The complex contains four interconnected main exhibition halls — EH101 through EH104 — plus outdoor event space and a convention wing. The show calendar focuses on industrial and process technology, pharmaceutical and personal care ingredients, laboratory science and medical devices. Most events at BITEC have their own organiser-issued exhibitor technical manual, which layers additional requirements on top of the venue's base regulations. The hall allocation for your stand — which of EH101–EH104 you are in — determines the applicable ceiling height, contractor entry point and service connection routing.

Event index

Shows at BITEC, Bang Na

METALEX

Metalworking Machinery · Biennial — November

Southeast Asia's largest metalworking and manufacturing machinery show. Heavy-equipment display, high floor loads, precision demonstration spaces and CNC machine integration are the defining build challenges.

Medical Fair Thailand

Medical Devices · Biennial — September

Medical device, diagnostics and hospital equipment event. Regulated product display environments, clinical aesthetics, consultation zones and careful separation of device categories govern stand design.

Thailand LAB INTERNATIONAL

Laboratory & Science · Annual — September

Analytical instruments, laboratory equipment and scientific services event. Live demonstration zones, precision counter layouts and instrument support requirements shape stand structure.

in-cosmetics Asia

Personal Care Ingredients · Annual — October/November

International personal care ingredient event. Ingredient sampling, textural experience stations and a demanding finish quality standard — visitors compare directly across adjacent stands.

COSMEX

Cosmetics OEM/ODM · Annual — October

Cosmetics OEM/ODM, finished goods and packaging event. Stand design frequently integrates product display shelving, sampling counters and formula-focused presentation zones.

Bangkok Gems & Jewelry Fair

Jewellery & Gems · Biannual — February and September

International gems, precious metals and finished jewellery trade event. Security requirements, high-value product display, lockable showcases and lighting precision are the stand-design priorities.

Technical data

Hall Specifications

Hall / AreaGross AreaClear HeightFloor LoadingNotes
EH101 – EH104 (combined)~60,000 sqm across four interconnected hallsVaries by hall — confirm with organiser before designingConfirm with organiser for your specific positionHalls can be used independently or combined. Ceiling height in the main halls is suited to single-level custom stands and, in specific halls, double-deck structures — verify which hall you are in before finalising elevations.
Convention WingConference rooms and ballroom — not primary exhibition spaceLower than exhibition hallsConvention floor loading; not suited to heavy machineryUsed for congresses, product launches and side events coinciding with main shows.

All figures are for orientation only. Confirm all specifications against the current official technical guide for your show.

Access windows

Build-up and Dismantling

Schedules are set by the organiser, not the venue

Build-up and dismantling windows at BITEC are allocated by each show organiser in the exhibitor technical manual — not by BITEC as a standing rule. Custom stand contractors typically receive earlier access than shell scheme exhibitors to accommodate longer build times. Overrunning the build-up window risks not opening on show day. Obtain the confirmed access schedule before finalising fabrication timelines.

Loading dock access and vehicle coordination

BITEC has designated cargo access gates for each hall, separate from visitor entrances. Large or heavy deliveries — machinery, structural steel, multiple crate loads — require advance coordination with the venue operations team. Standard 6-wheel trucks access without restriction; oversized vehicles require pre-approval. Plan delivery slots around the confirmed build-up schedule, not around assumptions about dock availability.

What commonly goes wrong

Materials delivered to the wrong cargo gate and re-routed. Structural drawings for double-deck approval submitted during build-up rather than before, adding review delays. Fire retardant certificates missing on arrival, causing materials to be held at the gate. Power ordered incorrectly or after the service deadline, resulting in supply that does not match the stand's load.

On-site access

Contractor Requirements

Exhibitor Contractor Badge (ECB)

All personnel entering the hall during build-up and dismantling must hold a valid ECB. Your appointed stand contractor registers all workers with the organiser, coordinating the submission of names and ID documents. Workers arriving without a valid ECB are denied hall entry. Submit worker lists to your contractor as early as the organiser asks — late submissions compress the available build window.

Insurance

Your appointed contractor must carry third-party liability insurance covering build-up, show days and dismantling. The minimum insured amount is set by each show organiser and stated in the exhibitor manual. The policy must name the correct parties as specified by the organiser. Confirm the requirement — and provide insurance documentation to your contractor — early.

Contractor deposit

Some BITEC shows require a refundable contractor deposit held against damage or failure to complete dismantling within the allocated window. The amount varies by show and is refunded upon satisfactory sign-off at the end of dismantling. Confirm whether your show requires a deposit and the release conditions before build-up begins.

What you can build

Stand Construction Rules

Stand height limits

Maximum stand height is set by the show organiser for each event — it is not a single blanket BITEC venue rule. The most common limit at BITEC shows is 4.5 m for freestanding structures, but individual shows in specific halls can permit higher structures with prior written approval and structural drawings. Confirm the applicable height limit for your show and your specific hall before finalising stand elevations.

Double-deck and raised structures

Raised floors, mezzanines and double-deck structures require structural engineering drawings, load calculations and a method statement submitted to the organiser before build-up begins. BITEC and/or the organiser must formally approve the structure before construction starts. Allow at least two to three weeks for the approval cycle — structural documentation submitted during build-up is too late.

Rigging from the ceiling

Hanging elements from the hall ceiling — fascias, suspended signs, lighting rigs — must be executed by BITEC's appointed rigging contractor. Self-rigging is not permitted. Submit a rigging plot (plan, section, suspension point weights and equipment list) to the organiser during stand design approval, not on arrival. Rigging is ordered through the official service form; lead times vary by show.

Fire retardant materials

All structural materials used in stand construction must be fire-retardant (FR) certified to the grade specified in the organiser's technical guide. Physical FR certificates — not digital copies — must be on site during BITEC's build-up inspection. Materials presented without FR documentation may be removed from the hall by the venue's safety team.

Finishing restrictions

Spray-painting and spray-finishing are not permitted inside BITEC's exhibition halls at any stage of build-up. All stand elements must arrive pre-finished from the fabrication workshop. Bring spare pre-finished panels for any repairs — on-site re-finishing is not an option. Exposed unfaced MDF, raw chipboard and unfinished edges are not acceptable at most BITEC shows.

Utilities and connectivity

Services and Ordering

Power ordering

Electrical supply is ordered through the organiser's official service form, with closing deadlines that vary by show. Standard supplies are 220 V / 50 Hz single-phase and 380 V / 50 Hz three-phase. Provide your contractor with a complete load schedule — covering all lighting, AV and powered equipment — before the order deadline. Late orders may not be fulfilled, or may incur a surcharge.

Water and drainage

Water supply and drainage connections are available in designated positions in some halls. Confirm whether a connection is available at your stand position before including a sink, tasting station or water feature in the design. Orders are placed through the official service form; connection positions are fixed and not negotiable on site.

Internet and AV

Dedicated bandwidth for exhibitor stands is available through the organiser's service order. Shared venue WiFi is unsuitable for in-stand demonstrations or video streaming. Order dedicated bandwidth early and specify the bandwidth allocation required for your AV setup. A cellular-based backup is worth adding for business-critical digital elements.

Freight and access

Logistics

Loading dock access

BITEC has multiple cargo access gates serving the exhibition halls, separate from visitor entrances. The specific gate and route depends on the hall you are in and the organiser's logistics plan. Using the wrong gate adds time; confirm your contractor's access route before build-up begins.

Forklift and lifting equipment

Forklift hire is available on site through BITEC's or the organiser's official service contractor. Bring-your-own forklifts require prior approval. For heavy items — machinery, large structural components — plan lifting equipment as part of the initial logistics plan, confirmed before the component is manufactured.

On-site storage during the show

All stand materials, packing crates and excess packaging must be cleared from the hall before the show opens. The organiser designates a storage area for contractor packing materials; space is limited. Plan your packaging strategy at the design stage — not on the morning of move-in.

Common questions

Frequently Asked Questions

Yes, but all ceiling rigging must be carried out by BITEC's appointed rigging contractor — self-rigging is not permitted. Submit a rigging plot (plan, section, suspension point weights and equipment specification) to the organiser during the stand approval process, not on arrival. Rigging has order lead times and costs; budget for it before the stand design is final.

BITEC is a well-regulated venue with consistent baseline requirements and show-specific layers applied by each organiser. The most common source of on-site difficulty is decisions deferred past the service manual deadline — FR documentation, power orders, rigging plots and structural drawings all need to be in place before build-up begins. The organiser's exhibitor manual for your specific show is the starting point. These specifications are reviewed periodically; always confirm current rules against the official exhibitor technical guide for your show and edition.

Free quotation within one working day

Planning a Stand at BITEC, Bang Na?

Send us your show name, space size and any structural requirements — we return a fixed, itemised quotation and initial concept within one working day, at no charge.

Pixelmate Exhibition Co., Ltd.

Typically replies within 1 business day

Hi there! Need an exhibition stand in Bangkok?
Drop us a message and let's talk about your project.
Chat on WhatsApp